Lakeway's Parks Bond, Two Years In: What's Open, What's Being Built, and What's Still Waiting

October 29, 2026

The newest play area in Lakeway, the playscape at the Lakeway Activity Center, came out of the smallest line in the city's parks bond. That line was $508,771 out of roughly $22 million. Since it opened, the city's parks director has estimated that it draws 50 to 100 people a day.

The largest line is $10.65 million for Lakeway City Park. As of October 2026, it is still a set of drawings. That gap explains the rest of the bond. Lakeway has worked through its five projects roughly from smallest to largest. The two finished or underway account for about 12% of the money. The other 88% belongs to the parks residents probably use most, and none of it has gone out to bid for construction yet.

The Bond, Ranked by Size and by Progress

In May 2024, 68% of Lakeway voters approved a $22 million parks bond. It covers four upgrades to existing parks and one new park in the Rough Hollow area. If you sort the projects by dollar amount and then by status, the order is easy to see.

Project Bond allocation Status as of October 2026
Lakeway Activity Center $508,771 Playscape finished September 2025
Butler Rough Hollow Park $2.1 million Under construction, opening expected in 2027
Lakeway City Park $10.65 million In design, construction bid estimated fall 2027
Lakeway Swim Center Park $6.02 million City looking for an aquatic engineering firm
Live Oak Tennis Courts $2.72 million Completion date "TBD"

The Activity Center and Butler Rough Hollow Park together come to about $2.6 million. City Park, the Swim Center and Live Oak together come to about $19.4 million.

The Small Project That Finished First

The Activity Center playscape is the only bond project you can use today. Community Impact reported in December 2025 that the work wrapped up that September. The playscape has natural play features for children of different ages, new landscaping and picnic areas. In the same report, Parks and Recreation Director Andra Bennett described the turnout as "good to know we hit the right chord with the community."

A small project with a short timeline was the logical place to start. Its quick success also set a benchmark for the rest of the bond.

A New Park Rising off Tomichi Trail

Butler Rough Hollow Park is the bond's only brand-new park, and it is the one with the most construction activity. The city's June 2026 newsletter announced a groundbreaking for Monday, July 6, at 708 Tomichi Trail. The construction contract went out for bids from Feb. 10 through April 1. City Council received nine bids and awarded the contract on April 20 to Millis Development and Construction, the lowest responsive bidder at $2,072,196. The highest bid was over $3.5 million.

According to the city, the park will include:

  • An amphitheater
  • A mountain bike course
  • A basketball area
  • A multisports field
  • A ninja course
  • A playground area

The final plan is smaller than what was first proposed. Community Impact reported that the design was scaled down because of cost, and that community conversations helped decide what stayed. Reports differ on the opening date. In April, Community Impact said construction should be completed by spring 2027. Its October update said the park is expected to open next summer. Either way, the park should be open within a year.

Butler also served as a trial run for the much larger City Park project. Dunaway, the engineering firm, held several open houses on Butler's design. City Manager Joseph Molis told Community Impact he wanted that process to "set the foundation" for how the city approaches City Park.

City Park Holds Nearly Half the Money

City Park's share of the bond is larger than the Swim Center and Live Oak combined. Most of the changes residents will notice depend on this one project. In November 2025, City Council approved a $1.02 million design contract with Dunaway, which estimated the design and engineering phase would take about a year and a half. Community Impact's October 2026 update reported that the city plans to finish design by January, with the construction bid estimated for fall 2027.

The current concept would change most of what people use at the park today:

  1. Getting around. A full vehicle loop and a looped pedestrian trail.
  2. Wheels. A new skate park and a pump track. An earlier concept also included a beginner bike skills park.
  3. Courts. New pickleball courts, plus a relocated sand volleyball court.
  4. Dogs. A relocated dog park with separate areas for large and small dogs.
  5. The lake. New overlook areas. An earlier concept called them overlook platforms and also included a boardwalk trail.

These plans are still at the concept stage. In December 2025, Molis told Community Impact that "there may be some choices that council has to make as far as what stays or what gets modified," and that the city would ask the community about its priorities before those decisions are made. Butler's design went through the same kind of review and came out smaller. For City Park, the list of features is likely to change more than its general shape.

Construction cannot start until after the fall 2027 bid. Until then, the dog park, volleyball court and skate park at City Park stay as they are.

The Last Two Still Waiting

The Swim Center comes after City Park. Its $6.02 million allocation is the second-largest in the bond. Community Impact reported in October that Bennett said the city is looking for a "unique engineering firm" for the pool project. A request for qualifications, the first step in hiring that firm, could be issued by early 2027. Because the designer has not been hired yet, nobody can say for certain what the finished Swim Center will include.

Live Oak Tennis Courts is last in line, by the city's own choice. A July 2025 city staff report placed the $2.72 million tennis project last in council priority, waiting on progress at the other parks. The newest project timeline, published in March 2026, still lists both Live Oak and the Swim Center with completion dates of "TBD."

Bennett summed up the city's approach in the October report: "We're trying to get these [projects] cranked out as fast as we can, and I say that with a caveat of making sure that we're doing quality parks and park projects in the process."

How the Bond Is Paid For

According to Community Impact, the 2024 proposition did not approve a specific tax increase, but it did allow the city to levy a tax to pay off the debt. For fiscal year 2025-26, Lakeway raised its overall tax rate by 6.16%. The debt portion of the rate rose 3.47% because of what the city called natural variations, which led to slightly higher principal and interest. City officials said the bond's tax impact has stayed the same. Most of what the bond pays for is still ahead, so the city's bid dates will tell you more about when that spending happens than the bond total does.

Rough Hollow Has Music Before It Has a Park

Butler Rough Hollow Park is still a year from opening, but Rough Hollow already has a regular evening event. The Big Band Bash at Rough Hollow is free and open to all ages on the second Monday of each month. Doors open at 6:30 p.m. and the music runs from 7 to 9 p.m. The next one falls on Nov. 9. The city's ArtWALK runs Nov. 6 through 8, and the city's October newsletter said registration was open for local artists.

A park that is a year from opening, or a redesign that won't go out to bid until fall 2027, can still affect what a nearby home is worth. If you would like to talk through how Butler Rough Hollow Park or the City Park plans relate to a property you own or are considering in Lakeway, Chris Hitchcock is glad to look at the timelines with you. Start a Conversation.