October 15, 2026
City leaders call Northline Leander's "new downtown." The first businesses lined up to open there are quick-lunch counters. Piada, Pepper Lunch, Tacodeli and Ike's Love & Sandwiches are all set for suites along East San Gabriel Parkway and the 183A frontage road, and all have construction windows ending in late 2026. The town square, the event stage and the festival promenade are still listed as planned amenities with no opening date.
That order matters because it shapes what the 116-acre site will be over the next two years. Permits and city notices filed through October 2026 show a set of fast-casual stops near the last station on CapMetro's Red Line arriving first. Dessert, a grocery anchor and city offices follow in 2027. The places where people gather have no published date at all.
The homes came first. The developer says the first residences opened in 2023. They include 25 finished Brownstone townhomes and the 343-unit Gramercy at Northline apartment community. The developer's site also lists the Northline Circle Civic Space and its first public art piece, a work called "Cascade."
The commercial part is behind schedule compared with early forecasts. KVUE's 2023 coverage said the first few retail shops were expected to open in 2025. In February 2026, the City of Leander said the first retail phase, 85,000 square feet of retail from Endeavor, was still under construction, and that more residential and commercial phases were in permitting. When KXAN filmed the site on September 30, 2026, it was still a construction zone.
As of October 6, no Northline restaurant or shop has a confirmed public opening. All of the dates below are permit windows or targets from the businesses, and the City says each business will announce its own opening.
These are the businesses closest to opening, listed by how far along their paperwork is:
Most of this group is counter service: tacos, sandwiches, hot-plate rice bowls, Italian street food and a drive-up coffee chain. These are quick weekday stops, and they are opening first, a short walk from Leander Station and a short drive from the Leander campus of Austin Community College. In practice, the 500 block of East San Gabriel Parkway will probably be a lunch spot well before it is a place people stay for the evening.
The 2027 announcements add the kinds of businesses that keep people around longer than a lunch break.
The other big 2027 project is a 95,000-square-foot office building scheduled for completion that year. The City plans to lease about 40,000 square feet of it for city offices. That puts a daytime workforce on site, and the weekday lunch counters from the first wave are set up to serve exactly that kind of crowd. A grocery store and a city office building also bring in steady weekday traffic. Many of the people a Sprouts draws will be there for a quick grocery run, which fits a district that will be busiest at midday for a while.
The heart of the original plan was supposed to be The Hub, a family entertainment venue. Plans called for about a dozen casual restaurants and bars around a large public space with a jumbotron and a pavilion stage, on three acres of retail space plus two acres of parking. The Hub stepped back in June 2023. Northline developer Alex Tynberg said financing problems kept it from breaking ground by the deadline the City required. CEO Brad Zeitlin said the company was focusing on its new location in Allen and that he hoped to rejoin Northline later. At the time, developers said the change would delay part of the project by about a year, and KVUE reported that they were negotiating with replacement retail anchors it did not name.
The pieces meant to fill the middle are listed as planned, and only some have dates:
The developer gives 2031 as the full buildout date. Put together, the dated pieces line up in a clear order. The lunch counters and coffee have construction windows over the next few months, and dessert and groceries are targeted for 2027. Marketplace businesses are expected in 2028, and Gringo's construction runs into February 2028. The town square, park and stage are the pieces with no published date.
You don't have to wait for Northline to try something new. Several places opened around town this year, and a few more are coming soon:
Most of these openings are along Ronald Reagan Boulevard and Southbrook Station. That's where Leander's new restaurants are appearing this year while Northline's first retail phase on San Gabriel Parkway is still under construction.
If you own a home near Northline, the order things open will shape your daily routine more than any single announcement will. Chris Hitchcock follows Northline's phasing as both an investor and a developer. If you'd like to talk through what the 2027 and 2028 phases could mean for your property, Start a Conversation.
Stay up to date on the latest real estate trends.
Austin's real estate market has changed considerably over the past few years.
Christopher Hitchcock builds, buys, manages, and sells real estate of his own. Every service he provides is backed by firsthand experience because he doesn’t just advise on real estate. He practices it.